New Hospital Update July 2010

* Exterior brick and stone are nearing completion (front & back of building)

* Window frames are installed in most areas and glass will be added within the next couple of weeks.

* Beginning to hang drywall in the south and west sections (Maintenance, Materials Management, Information Services, Environmental Services, Operating Rooms, and Medical-Surgical Unit.




Steel studs, which divide the rooms, are going up in the rest of the building.

* Black dirt being added in areas around the building.